Big Bush Park Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground, spray shower, handball courts, sitting area, fencing and pavements in Big Bush Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2014
Projected Completion Date:
December 2015
Completion Date:
March 2016
Procurement
Start Date: March 2016
Projected Completion Date:
December 2016
Completion
Date:
February 2017
Construction
Start Date: May 2017
Projected Completion Date:
April 2018
Completion Date: May 2018
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Big Bush Playground, Queens
Laurel Hill Boulevard between 61st Street and 64th Street
Community Board: 02
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025