Big Bush Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, spray shower, handball courts, sitting area, fencing and pavements in Big Bush Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2014
Projected Completion Date: December 2015
Completion Date: March 2016

Procurement

Start Date: March 2016
Projected Completion Date: December 2016
Completion Date: February 2017

Construction

Start Date: May 2017
Projected Completion Date: April 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $1,683,000
Funding Sources:
  • Borough President
  • City Council

Location

Big Bush Playground, Queens
Laurel Hill Boulevard between 61st Street and 64th Street
Community Board: 02

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025