Joe Devoy Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Joe Devoy Playground in Forest Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2014
Projected Completion Date:
August 2015
Completion Date:
September 2015
Procurement
Start Date: September 2015
Projected Completion Date:
June 2016
Completion
Date:
April 2016
Construction
Start Date: June 2016
Projected Completion Date:
June 2017
Completion Date: January 2017
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Forest Park, Queens
Union Turnpike and 71st Avenue
Community Board: 05, 05, 06, 09
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025