Bowne Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and basketball court in Bowne Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2014
Projected Completion Date: August 2015
Completion Date: August 2015

Procurement

Start Date: August 2015
Projected Completion Date: May 2016
Completion Date: June 2016

Construction

Start Date: August 2016
Projected Completion Date: August 2017
Completion Date: August 2017

Understand how we build parks.

Funding

Total Funding: $1,411,000
Funding Sources:
  • Borough President
  • City Council

Location

Bowne Park, Queens
155th Street, 159th Street, 29th Avenue, 32nd Avenue
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025