Roy Wilkins Recreation Center Gymnasium Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the gymnasium and access ramps at Roy Wilkins Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2016
Projected Completion Date: June 2017
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: March 2019
Completion Date: November 2019

Construction

Start Date: September 2020
Projected Completion Date: March 2022
Completion Date: March 2022

Understand how we build parks.

Funding

Total Funding: $2,736,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Roy Wilkins Recreation Center, Queens
177-01 Baisley Boulevard
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025