Bayside Historical Society Officers Club Porch Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the front portico at the Bayside Historical Society Officers Club in Fort Totten Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2015
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: December 2017

Construction

Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $297,000
Funding Source: City Council

Location

Fort Totten Park, Queens
208 Totten Avenue
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024