Canarsie West Trail Connector Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a multi-use greenway path connecting the on-street path along Paerdegat Avenue North to the Shore Parkway Greenway along the southwestern edge of Canarsie Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2014
Projected Completion Date: October 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: April 2017

Construction

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $1,230,000
Funding Source: Federal

Location

Canarsie Park, Brooklyn
Paerdegat Avenue North & Seaview Avenue to Shore Parkway
Community Board: 18

 

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024