Morningside Park 123rd Street Playground Reconstruction Phase 2

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play equipment, seating, planting, lighting, pavements, fencing, and drainage and water supply systems at 123rd Street Playground in Morningside Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2015
Projected Completion Date: November 2016
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: January 2018
Completion Date: December 2017

Construction

Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $2,447,000
Funding Source: City Council

Location

Morningside Park, Manhattan
West 123rd Street and Morningside Avenue
Community Board: 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025