Morningside Park 123rd Street Playground Reconstruction Phase 2
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play equipment, seating, planting, lighting, pavements, fencing, and drainage and water supply systems at 123rd Street Playground in Morningside Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2015
Projected Completion Date:
November 2016
Completion Date:
April 2017
Procurement
Start Date: April 2017
Projected Completion Date:
January 2018
Completion
Date:
December 2017
Construction
Start Date: March 2018
Projected Completion Date:
March 2019
Completion Date: March 2019
Understand how we build parks.
Funding
Funding Source: City Council
Location
Morningside Park, Manhattan
West 123rd Street and Morningside Avenue
Community Board: 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025