Theodore Roosevelt Park Dog Run Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Bull Moose Dog Run in Theodore Roosevelt Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2017
Projected Completion Date:
June 2018
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
June 2019
Construction
Start Date: July 2019
Projected Completion Date:
July 2020
Completion Date: July 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Theodore Roosevelt Park, Manhattan
West 81st Street and Central Park West
Community Board: 07
Project Staff
Project Liaison: Steve Simon