Sara D. Roosevelt Park Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct a Public restroom building in building A in Sara D Roosevelt Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2016
Projected Completion Date:
October 2017
Completion Date:
November 2017
Procurement
Start Date: November 2017
Projected Completion Date:
August 2018
Completion
Date:
December 2018
Construction
Start Date: January 2019
Projected Completion Date:
January 2020
Completion Date: January 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Sara D. Roosevelt Park, Manhattan
Stanton Street between Chrystie Street and Forsyth Street
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024