Sara D. Roosevelt Park Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct a Public restroom building in building A in Sara D Roosevelt Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2016
Projected Completion Date: October 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018
Completion Date: December 2018

Construction

Start Date: January 2019
Projected Completion Date: January 2020
Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $1,417,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Sara D. Roosevelt Park, Manhattan
Stanton Street between Chrystie Street and Forsyth Street
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024