Seaside Wildlife Nature Park Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    68% complete

This project will construct a public restroom building in Seaside Wildlife Nature Park

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2018
Projected Completion Date: December 2019
Completion Date: June 2020

Procurement

Start Date: June 2020
Projected Completion Date: March 2021
Completion Date: February 2023

Construction

Start Date: July 2023
Projected Completion Date: January 2025

Understand how we build parks.

Funding

Total Funding: $6,765,000
Funding Sources:
  • City Council
  • Mayoral

Location

Seaside Wildlife Nature Park, Staten Island
Nelson Avenue at Tennyson Drive
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025