Seaside Wildlife Nature Park Public Restroom Building Construction
-
100% complete
-
100% complete
-
50% complete
This project will construct a public restroom building in Seaside Wildlife Nature Park
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2018
Projected Completion Date:
December 2019
Completion Date:
June 2020
Procurement
Start Date: June 2020
Projected Completion Date:
March 2021
Completion
Date:
February 2023
Construction
Start Date: July 2023
Projected Completion Date:
January 2025
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Seaside Wildlife Nature Park, Staten Island
Nelson Avenue at Tennyson Drive
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024