Seaside Wildlife Nature Park Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    50% complete

This project will construct a public restroom building in Seaside Wildlife Nature Park

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2018
Projected Completion Date: December 2019
Completion Date: June 2020

Procurement

Start Date: June 2020
Projected Completion Date: March 2021
Completion Date: February 2023

Construction

Start Date: July 2023
Projected Completion Date: January 2025

Understand how we build parks.

Funding

Total Funding: $6,765,000
Funding Sources:
  • City Council
  • Mayoral

Location

Seaside Wildlife Nature Park, Staten Island
Nelson Avenue at Tennyson Drive
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024