Baruch Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building at Baruch Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2015
Projected Completion Date: January 2017
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: May 2018

Construction

Start Date: August 2018
Projected Completion Date: January 2020
Completion Date: December 2021

Understand how we build parks.

Funding

Total Funding: $1,928,000
Funding Sources:
  • City Council
  • Mayoral

Location

Baruch Playground, Manhattan
Baruch Place and Rivington Street
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025