Inwood Hill Park Nature Center Sewer Connection Construction
-
100% complete
-
100% complete
-
100% complete
This project will install a sewer line between Inwood Hill Nature Center and West 218th Street.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2014
Projected Completion Date:
August 2015
Completion Date:
January 2016
Procurement
Start Date: January 2016
Projected Completion Date:
October 2016
Completion
Date:
March 2017
Construction
Start Date: July 2017
Projected Completion Date:
July 2018
Completion Date: July 2018
Understand how we build parks.
Funding
Funding Source: City Council
Location
Inwood Hill Park, Manhattan
Indian Road and West 218th Street
Community Board: 12
Project Staff
Project Liaison: Steve Simon