Albano Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    94% complete

This project will reconstruct the play equipment, safety surfacing, handball courts, and asphalt multi-purpose play area and construct a new spray shower at Albano Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: August 2017
Completion Date: April 2022

Procurement

Start Date: April 2022
Projected Completion Date: May 2018
Completion Date: September 2023

Construction

Start Date: November 2023
Projected Completion Date: November 2024

Understand how we build parks.

Funding

Total Funding: $1,550,000
Funding Sources:
  • Borough President
  • City Council

Location

Vincent F. Albano Jr. Playground, Manhattan
East 29th Street and 2nd Avenue
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024