Seravalli Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building at Seravalli Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2014
Projected Completion Date: March 2016
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: April 2017
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: March 2019
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $1,034,000
Funding Source: City Council

Location

Corporal John A. Seravalli Playground, Manhattan
Hudson Street between Gansevoort Street and Horatio Street
Community Board: 02

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024