Seravalli Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building at Seravalli Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2014
Projected Completion Date:
March 2016
Completion Date:
August 2016
Procurement
Start Date: August 2016
Projected Completion Date:
April 2017
Completion
Date:
June 2017
Construction
Start Date: September 2017
Projected Completion Date:
March 2019
Completion Date: July 2019
Understand how we build parks.
Funding
Funding Source: City Council
Location
Corporal John A. Seravalli Playground, Manhattan
Hudson Street between Gansevoort Street and Horatio Street
Community Board: 02
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024