Marcus Garvey Park Fire Watchtower Restoration

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the fire watchtower and surrounding plaza in Marcus Garvey Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: October 2015
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: November 2016
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $7,970,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Marcus Garvey Park, Manhattan
Madison Avenue at East 122nd Street
Community Board: 11

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project