Arrochar Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and multi-use area at Arrochar Playground adjacent to PS 39.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: January 2016
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: July 2016

Construction

Start Date: August 2016
Projected Completion Date: November 2017
Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $3,101,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Arrochar Playground, Staten Island
Sand Lane between Major Avenue and MacFarland Avenue
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024