Joseph Austin Playground Synthetic Turf Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the synthetic turf ballfield and drainage system at Joe Austin Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2015
Projected Completion Date:
March 2016
Completion Date:
May 2016
Procurement
Start Date: May 2016
Projected Completion Date:
February 2017
Completion
Date:
July 2017
Construction
Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date: June 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Joseph Austin Playground, Queens
Grand Central Parkway, 164th Place, 168th Street
Community Board: 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025