Joseph Austin Playground Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf ballfield and drainage system at Joe Austin Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2015
Projected Completion Date: March 2016
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: February 2017
Completion Date: July 2017

Construction

Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $2,670,000
Funding Source: Mayoral

Location

Joseph Austin Playground, Queens
Grand Central Parkway, 164th Place, 168th Street
Community Board: 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024