Brownsville Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    38% complete

This project will reconstruct the interior and infrastructure of Brownsville Recreation Center.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2016
Projected Completion Date: May 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Completion Date: January 2022

Construction

Start Date: March 2022

Understand how we build parks.

Funding

Total Funding: $20,259,000
Funding Source: Mayoral

Location

Brownsville Playground, Brooklyn
1555 Linden Boulevard
Community Board: 16

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project