Brooklyn and Staten Island Reforestation FY15

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove invasive species and plant new trees in Brooklyn and Staten Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2014
Projected Completion Date: August 2014
Completion Date: September 2014

Procurement

Start Date: September 2014
Projected Completion Date: June 2015
Completion Date: June 2015

Construction

Start Date: April 2015
Projected Completion Date: October 2017
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $1,030,000
Funding Sources:
  • Mayoral
  • Private

Location

Various parks in Brooklyn and Staten Island

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025