Lost Battalion Hall Recreation Center Reconstruction
-
100% complete
-
100% complete
-
75% complete
This project will reconstruct Lost Battalion Hall Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
January 2021
Completion
Date:
March 2022
Construction
Start Date: July 2022
Projected Completion Date:
January 2024
Adjusted Completion Date: March 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Lost Battalion Hall Recreation Center, Queens
Queens Boulevard between 62nd Avenue and 62nd Drive
Community Board: 06
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024