Lost Battalion Hall Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    78% complete

This project will reconstruct Lost Battalion Hall Recreation Center.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021
Completion Date: March 2022

Construction

Start Date: July 2022
Projected Completion Date: January 2024
Adjusted Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $25,816,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Lost Battalion Hall Recreation Center, Queens
Queens Boulevard between 62nd Avenue and 62nd Drive
Community Board: 06

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025