Lost Battalion Hall Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    75% complete

This project will reconstruct Lost Battalion Hall Recreation Center.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021
Completion Date: March 2022

Construction

Start Date: July 2022
Projected Completion Date: January 2024
Adjusted Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $25,904,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Lost Battalion Hall Recreation Center, Queens
Queens Boulevard between 62nd Avenue and 62nd Drive
Community Board: 06

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024