Tony Dapolito Recreation Center Stabilization
-
100% complete
-
100% complete
-
PAUSED
This project will stabilize the Tony Dapolito Recreation Center
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2017
Projected Completion Date:
June 2018
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
September 2019
Construction
Start Date: September 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Tony Dapolito Recreation Center, Manhattan
Clarkson Street and Seventh Avenue South
Community Board: 02
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024