Tony Dapolito Recreation Center Stabilization
-
100% complete
-
100% complete
-
PAUSED
This project will stabilize the Tony Dapolito Recreation Center
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2017
Projected Completion Date:
June 2018
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
September 2019
Construction
Start Date: September 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Tony Dapolito Recreation Center, Manhattan
Clarkson Street and Seventh Avenue South
Community Board: 02
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025