Hansborough Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    39% complete

This project will reconstruct the pool, entrance and interior spaces of the Hansborough Recreation Center.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2020
Projected Completion Date: March 2021
Completion Date: March 2022

Procurement

Start Date: March 2022
Projected Completion Date: December 2022
Completion Date: January 2024

Construction

Start Date: March 2024
Projected Completion Date: March 2026

Understand how we build parks.

Funding

Total Funding: $70,890,000
Funding Sources:
  • City Council
  • Mayoral
  • State

Location

Hansborough Recreation Center, Manhattan
35 West 134th Street between Lenox Terrace and 5th Avenue.
Community Board: 10

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project