Sunset Park Bathhouse Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    58% complete

This project will reconstruct the bathhouse in Sunset Park.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2015
Projected Completion Date: September 2017
Completion Date: September 2021

Procurement

Start Date: September 2021
Projected Completion Date: June 2022
Completion Date: April 2023

Construction

Start Date: September 2023
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $11,521,000
Funding Sources:
  • City Council
  • Mayoral

Location

Sunset Park, Brooklyn
7th Avenue between 41st Street and 44th Street
Community Board: 07

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025