Sunset Park Bathhouse Reconstruction
-
100% complete
-
100% complete
-
58% complete
This project will reconstruct the bathhouse in Sunset Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2015
Projected Completion Date:
September 2017
Completion Date:
September 2021
Procurement
Start Date: September 2021
Projected Completion Date:
June 2022
Completion
Date:
April 2023
Construction
Start Date: September 2023
Projected Completion Date:
March 2025
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Sunset Park, Brooklyn
7th Avenue between 41st Street and 44th Street
Community Board: 07
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025