Sunset Park Bathhouse Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    32% complete

This project will reconstruct the bathhouse in Sunset Park.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2015
Projected Completion Date: September 2017
Completion Date: September 2021

Procurement

Start Date: September 2021
Projected Completion Date: June 2022
Completion Date: April 2023

Construction

Start Date: September 2023
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $10,201,000
Funding Sources:
  • City Council
  • Mayoral

Location

Sunset Park, Brooklyn
7th Avenue between 41st Street and 44th Street
Community Board: 07

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024