Sunset Park Bathhouse Reconstruction
-
100% complete
-
100% complete
-
32% complete
This project will reconstruct the bathhouse in Sunset Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2015
Projected Completion Date:
September 2017
Completion Date:
September 2021
Procurement
Start Date: September 2021
Projected Completion Date:
June 2022
Completion
Date:
April 2023
Construction
Start Date: September 2023
Projected Completion Date:
March 2025
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Sunset Park, Brooklyn
7th Avenue between 41st Street and 44th Street
Community Board: 07
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project