St. Mary's Park Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    58% complete

This project will reconstruct St. Mary's Park Recreation Center.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2015
Projected Completion Date: September 2017
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021
Completion Date: March 2022

Construction

Start Date: May 2022
Projected Completion Date: November 2023
Adjusted Completion Date: January 2026

Understand how we build parks.

Funding

Total Funding: $11,523,000
Funding Source: Mayoral

Location

St. Mary's Park, Bronx
St. Anns Avenue between East 145th and East 147th Streets.
Community Board: 01

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025