St. Mary's Park Recreation Center Reconstruction
-
100% complete
-
100% complete
-
58% complete
This project will reconstruct St. Mary's Park Recreation Center.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2015
Projected Completion Date:
September 2017
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
January 2021
Completion
Date:
March 2022
Construction
Start Date: May 2022
Projected Completion Date:
November 2023
Adjusted Completion Date: January 2026
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
St. Mary's Park, Bronx
St. Anns Avenue between East 145th and East 147th Streets.
Community Board: 01
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025