St. Mary's Park Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    51% complete

This project will reconstruct St. Mary's Park Recreation Center.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2015
Projected Completion Date: September 2017
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021
Completion Date: March 2022

Construction

Start Date: May 2022
Projected Completion Date: November 2023
Adjusted Completion Date: April 2025

Understand how we build parks.

Funding

Total Funding: $12,054,000
Funding Source: Mayoral

Location

St. Mary's Park, Bronx
St. Anns Avenue between East 145th and East 147th Streets.
Community Board: 01

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024