Conference House Park Beaches Emergency Protective Measures (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will repair emergency protective measures in Conference House Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2014
Completion Date:
June 2014
Procurement
Start Date: June 2014
Projected Completion Date:
March 2015
Completion
Date:
November 2014
Construction
Start Date: December 2014
Projected Completion Date:
May 2015
Completion Date: February 2015