Bronx General Site Work (XG-514M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct parks, playgrounds and site work at various sites in the Bronx.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2014
Projected Completion Date:
June 2014
Completion Date:
September 2014
Procurement
Start Date: September 2014
Projected Completion Date:
June 2015
Completion
Date:
August 2015
Construction
Start Date: September 2015
Projected Completion Date:
March 2017
Completion Date: February 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Allerton Playground, Bronx
Allerton Ave. bet. Throop Ave. and Bouck Ave.
Community Board: 11 -
Eastchester Playground, Bronx
Adee Ave. at Tenboeck Ave.
Community Board: 11 -
Lozada Playground, Bronx
E 135 St bet Alex&er Av and Willis Av
Community Board: 01 -
Mazzei Playground, Bronx
Mace Ave. bet. Pauldings Ave. and Williamsbridge Rd.
Community Board: 11 -
Willis Playground, Bronx
E 141 St to E 140 St bet Willis Av & Alexander Av
Community Board: 01 -
La Finca del Sur Community Garden, Bronx
E. 138 St., Grand Concourse, Railroad tracks