Bronx General Site Work (XG-514M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct parks, playgrounds and site work at various sites in the Bronx.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2014
Projected Completion Date: June 2014
Completion Date: September 2014

Procurement

Start Date: September 2014
Projected Completion Date: June 2015
Completion Date: August 2015

Construction

Start Date: September 2015
Projected Completion Date: March 2017
Completion Date: February 2017

Understand how we build parks.

Funding

Total Funding: $2,055,000
Funding Source: Mayoral

Locations

  • Allerton Playground, Bronx
    Allerton Ave. bet. Throop Ave. and Bouck Ave.
    Community Board: 11
  • Eastchester Playground, Bronx
    Adee Ave. at Tenboeck Ave.
    Community Board: 11
  • Lozada Playground, Bronx
    E 135 St bet Alex&er Av and Willis Av
    Community Board: 01
  • Mazzei Playground, Bronx
    Mace Ave. bet. Pauldings Ave. and Williamsbridge Rd.
    Community Board: 11
  • Willis Playground, Bronx
    E 141 St to E 140 St bet Willis Av & Alexander Av
    Community Board: 01
  • La Finca del Sur Community Garden, Bronx
    E. 138 St., Grand Concourse, Railroad tracks
 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project