Crotona Pool Wall and Fence Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will demolish and reconstruct the steel fence and perimeter wall around the pool in Crotona Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2014
Projected Completion Date:
February 2016
Completion Date:
May 2017
Procurement
Start Date: May 2017
Projected Completion Date:
February 2018
Completion
Date:
May 2018
Construction
Start Date: August 2018
Projected Completion Date:
August 2019
Completion Date: August 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Crotona Park, Bronx
Fulton Avenue bewteen East 172nd Street and East 173rd Street
Community Board: 03
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025