Citywide Steel Guiderails, Timber Rails and Fencing Installation (CNYG-1414M)
-
100% complete
-
100% complete
-
100% complete
This project will install steel-beam guiderails, timber barrier rails, and fencing at various parks citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2014
Projected Completion Date:
May 2014
Completion Date:
July 2014
Procurement
Start Date: July 2014
Projected Completion Date:
April 2015
Completion
Date:
December 2015
Construction
Start Date: March 2016
Projected Completion Date:
March 2019
Completion Date: October 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Forest Park, Queens
Myrtle Ave., Union Turnpike, Park Lane South bet. Brooklyn-Queens County Line and Park Lane
Community Board: 05, 05, 06, 09 -
Highland Park, Queens
Jacke Robinson Parkway to Highland Boulevard / West of Vermont Place / East of Red Brick Structure and Natural Area
Community Board: 05, 05 -
Kissena Park, Queens
Booth Memorial Avenue between Kissena Boulevard & 162nd Street including Velodrome and Parking Lot
Community Board: 07 -
Spring Creek Park, Brooklyn
Fountain Ave., 75 St. bet. Belt Pkwy., Flatlands Ave.,
Community Board: 05, 10
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024