Citywide Steel Guiderails, Timber Rails and Fencing Installation (CNYG-1414M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install steel-beam guiderails, timber barrier rails, and fencing at various parks citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2014
Projected Completion Date: May 2014
Completion Date: July 2014

Procurement

Start Date: July 2014
Projected Completion Date: April 2015
Completion Date: December 2015

Construction

Start Date: March 2016
Projected Completion Date: March 2019
Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $975,000
Funding Source: Mayoral

Locations

  • Forest Park, Queens
    Myrtle Ave., Union Turnpike, Park Lane South bet. Brooklyn-Queens County Line and Park Lane
    Community Board: 05, 05, 06, 09
  • Highland Park, Queens
    Jacke Robinson Parkway to Highland Boulevard / West of Vermont Place / East of Red Brick Structure and Natural Area
    Community Board: 05, 05
  • Kissena Park, Queens
    Booth Memorial Avenue between Kissena Boulevard & 162nd Street including Velodrome and Parking Lot
    Community Board: 07
  • Spring Creek Park, Brooklyn
    Fountain Ave., 75 St. bet. Belt Pkwy., Flatlands Ave.,
    Community Board: 05, 10
 