Bronx General Site Work (XG-315M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the concrete sidewalks and complete other related site work at various locations in the Bronx.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: March 2015
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: February 2016
Completion Date: May 2016

Construction

Start Date: June 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Understand how we build parks.

Funding

Total Funding: $1,300,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

  • Bicentennial Veterans Memorial Park, Bronx
    Throgg's Neck Exwy at Pennyfield Ave. and Elisworth Ave.
    Community Board: 10
  • Bufano Park, Bronx
    Bradford Ave. bet. La Salle Ave. and Waterbury Ave.
    Community Board: 10
  • Pelham Bay Park, Bronx
    Hutchinson River, Long Island Sound bet. Bronc County Line and Middletown Rd., Watt Ave.
    Community Board: 10, 12
  • Vidalia Park, Bronx
    E. 180 St. bet. Daly Ave. and Vyse Ave.
    Community Board: 06
  • Vinmont Veteran Park, Bronx
    W. 254 St. bet Riverdale Ave. and Mosholu Ave.
    Community Board: 08
 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024