Harris Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the park's perimeter lawn area, construct four (4) sets of steel signage, and construct a storm sewer connection.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: June 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: October 2016

Construction

Start Date: February 2017
Projected Completion Date: February 2018
Completion Date: February 2018

Understand how we build parks.

Funding

Total Funding: $578,000
Funding Source: Mayoral

Location

Harris Park, Bronx
Harris Park located between Goulden and Paul Avenues and West 205th Street and Bedford Park Boulevard
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024