Harris Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the park's perimeter lawn area, construct four (4) sets of steel signage, and construct a storm sewer connection.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2014
Projected Completion Date:
June 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
October 2016
Construction
Start Date: February 2017
Projected Completion Date:
February 2018
Completion Date: February 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Harris Park, Bronx
Harris Park located between Goulden and Paul Avenues and West 205th Street and Bedford Park Boulevard
Community Board: 07