Faber Pool and Lyons Pool Boiler Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the boilers and heating systems at Faber Pool and Lyons Pool.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2014
Projected Completion Date:
January 2015
Completion Date:
June 2015
Procurement
Start Date: June 2015
Projected Completion Date:
March 2016
Completion
Date:
October 2016
Construction
Start Date: January 2017
Projected Completion Date:
February 2018
Completion Date: July 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Faber Pool and Park, Staten Island
Richmond Ter. To Kill Van Kull, Faber St.
Community Board: 01 -
Lyons Pool, Staten Island
Murray Hulbert Avenue between Victory Boulevard and Hannah Street
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 01/17/2025