Faber Pool and Lyons Pool Boiler Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the boilers and heating systems at Faber Pool and Lyons Pool.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2014
Projected Completion Date: January 2015
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: October 2016

Construction

Start Date: January 2017
Projected Completion Date: February 2018
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $1,994,000
Funding Source: Mayoral

Locations

  • Faber Pool and Park, Staten Island
    Richmond Ter. To Kill Van Kull, Faber St.
    Community Board: 01
  • Lyons Pool, Staten Island
    Murray Hulbert Avenue between Victory Boulevard and Hannah Street
    Community Board: 01
 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025