Police Officer Nicholas Demutiis Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground in Police Officer Nicholas Demutiis Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: December 2014
Completion Date: October 2015

Procurement

Start Date: October 2015
Projected Completion Date: July 2016
Completion Date: October 2016

Construction

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: August 2017

Understand how we build parks.

Funding

Total Funding: $1,774,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Police Officer Nicholas Demutiis Park, Queens
101st Street and Liberty Avenue
Community Board: 10

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024