Arsenal Building Facade and Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the facade and roof at the Arsenal building in Central Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: March 2017

Procurement

Start Date: March 2017
Projected Completion Date: December 2017
Completion Date: January 2018

Construction

Start Date: March 2018
Projected Completion Date: September 2019
Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $2,369,000
Funding Source: Mayoral

Location

Central Park, Manhattan
Fifth Avenue and East 64th Street
Community Board: 10, 11, 07, 05, 08, 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024