Staten Island Building Demolition (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will demolish four buildings in Staten Island, including 850 Page Avenue, two bungalows at Cedar Grove Beach and the New Springville Storehouse, all damaged from Hurricane Sandy.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2014
Projected Completion Date:
June 2014
Completion Date:
July 2014
Procurement
Start Date: July 2014
Projected Completion Date:
March 2015
Completion
Date:
July 2015
Construction
Start Date: September 2015
Projected Completion Date:
September 2016
Completion Date: March 2016
Understand how we build parks.
Funding
Locations
-
Conference House Park, Staten Island
Shore Road, Satterlee Street, Massachusetts, Surf, Billop Avenues, Brighton Street
Community Board: 03 -
Freshkills Park, Staten Island
Victory Boulevard, Signs Road, Travis Avenue, Arthur Kill Road
Community Board: 02 -
Great Kills Park, Staten Island
Hylan, Fairlawn to Emmet, Cedar Grove to New Dorp.
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 01/17/2025