Jane Street Garden Fence Construction and Jackson Square Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new fence at Jane Street Garden and reconstruct Jackson Square Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2014
Projected Completion Date: April 2015
Completion Date: March 2017

Procurement

Start Date: March 2017
Projected Completion Date: December 2017
Completion Date: December 2017

Construction

Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $2,282,000
Funding Sources:
  • City Council
  • Mayoral

Locations

  • Jackson Square, Manhattan
    8 Ave. To Greenwich Ave., Horatio St.
    Community Board: 02
  • Jane Street Garden, Manhattan
    Jane St. at 8th Ave.
 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project