Broadway Malls Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct landscapes, pavements, fences and benches at several malls along Broadway from West 102nd to 104th Streets and from West 137th to 139th Streets.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2015
Projected Completion Date:
September 2016
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
June 2018
Construction
Start Date: August 2018
Projected Completion Date:
August 2019
Completion Date: December 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Locations
-
Broadway Malls, Manhattan
Broadway, Columbus Circle to West 110 Street
Community Board: 04, 07 -
Broadway Malls, Manhattan
Broadway, West 135 Street to West 156 Streets
Community Board: 09, 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025