Broadway Malls Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct landscapes, pavements, fences and benches at several malls along Broadway from West 102nd to 104th Streets and from West 137th to 139th Streets.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2015
Projected Completion Date: September 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: June 2018

Construction

Start Date: August 2018
Projected Completion Date: August 2019
Completion Date: December 2020

Understand how we build parks.

Funding

Total Funding: $1,576,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

  • Broadway Malls, Manhattan
    Broadway, Columbus Circle to West 110 Street
    Community Board: 04, 07
  • Broadway Malls, Manhattan
    Broadway, West 135 Street to West 156 Streets
    Community Board: 09, 12
 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025