St. Gregory's Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct St. Gregory's Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2015
Projected Completion Date:
November 2015
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
July 2018
Construction
Start Date: August 2018
Projected Completion Date:
August 2019
Completion Date: September 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
St. Gregory's Playground, Manhattan
West 90th Street between Amsterdam and Columbus Avenues
Community Board: 07
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024