St. Gregory's Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct St. Gregory's Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2015
Projected Completion Date: November 2015
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: July 2018

Construction

Start Date: August 2018
Projected Completion Date: August 2019
Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $1,124,000
Funding Sources:
  • City Council
  • Mayoral

Location

St. Gregory's Playground, Manhattan
West 90th Street between Amsterdam and Columbus Avenues
Community Board: 07

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project