Parque de los Ninos Softball Field and Running Track Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the softball field with a natural grass outfield and a running track with artificial turf multiuse infield at Parque de los Ninos.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: March 2016
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: January 2017
Completion Date: May 2018

Construction

Start Date: August 2018
Projected Completion Date: August 2019
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $3,854,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Bronx River Parkway, Bronx
Metcalf Avenue between Watson and Westchester Avenues
Community Board: 06, 09, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024