Greencroft Playground Public Restroom Building Construction
-
100% complete
-
100% complete
-
100% complete
This project will demolish the existing public restroom building and construct a new comfort station at Greencroft Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2015
Projected Completion Date:
June 2016
Completion Date:
July 2017
Procurement
Start Date: July 2017
Projected Completion Date:
April 2018
Completion
Date:
October 2019
Construction
Start Date: December 2019
Projected Completion Date:
June 2021
Completion Date: October 2022
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Greencroft Playground, Staten Island
Greencroft Avenue Between Redgrave Avenue and Ainsworth Avenue
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024