Greencroft Playground Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will demolish the existing public restroom building and construct a new comfort station at Greencroft Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2015
Projected Completion Date: June 2016
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Completion Date: October 2019

Construction

Start Date: December 2019
Projected Completion Date: June 2021
Completion Date: October 2022

Understand how we build parks.

Funding

Total Funding: $3,301,000
Funding Sources:
  • Borough President
  • City Council

Location

Greencroft Playground, Staten Island
Greencroft Avenue Between Redgrave Avenue and Ainsworth Avenue
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024