Travers Park and Staunton Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the asphalt play fields in Travers Park and Staunton Field, and construct a plaza within the 78th Street right-of-way.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2014
Projected Completion Date:
October 2015
Completion Date:
November 2016
Procurement
Start Date: November 2016
Projected Completion Date:
August 2017
Completion
Date:
November 2017
Construction
Start Date: March 2018
Projected Completion Date:
September 2019
Completion Date: August 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Locations
-
Rory Staunton Field, Queens
78 St., 79 St. bet Northern Blvd. and 34 Ave.
Community Board: 03 -
Travers Park, Queens
34 Ave. bet. 77 St. and 78 St.
Community Board: 03
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025