Travers Park and Staunton Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the asphalt play fields in Travers Park and Staunton Field, and construct a plaza within the 78th Street right-of-way.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: October 2015
Completion Date: November 2016

Procurement

Start Date: November 2016
Projected Completion Date: August 2017
Completion Date: November 2017

Construction

Start Date: March 2018
Projected Completion Date: September 2019
Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $6,013,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

  • Rory Staunton Field, Queens
    78 St., 79 St. bet Northern Blvd. and 34 Ave.
    Community Board: 03
  • Travers Park, Queens
    34 Ave. bet. 77 St. and 78 St.
    Community Board: 03
 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024