Glick Park Electrical Systems Reconstruction (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the electrical systems at Glick Park due to damage from Hurricane Sandy.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2015
Projected Completion Date:
January 2017
Completion Date:
April 2017
Procurement
Start Date: April 2017
Projected Completion Date:
December 2017
Completion
Date:
May 2018
Construction
Start Date: June 2018
Projected Completion Date:
June 2019
Completion Date: June 2019
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
East River Esplanade, Manhattan
East River between East 36th and East 38th Streets
Community Board: 06
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024