Glick Park Electrical Systems Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the electrical systems at Glick Park due to damage from Hurricane Sandy.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2015
Projected Completion Date: January 2017
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: December 2017
Completion Date: May 2018

Construction

Start Date: June 2018
Projected Completion Date: June 2019
Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $732,000
Funding Sources:
  • Federal
  • Mayoral

Location

East River Esplanade, Manhattan
East River between East 36th and East 38th Streets
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024