Design
Assigned & Start Date: February 2014
Projected Completion Date:
March 2014
Completion Date:
July 2014
Procurement
Start Date: July 2014
Projected Completion Date:
April 2015
Completion
Date:
June 2015
Construction
Start Date: September 2015
Projected Completion Date:
September 2016
Completion Date: October 2016
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Washington Square Park, Manhattan
Waverly Place, West 4th Street, University Place and Macdougal Street
Community Board: 02
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024