Carmansville Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Carmansville Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2013
Projected Completion Date:
July 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
August 2016
Construction
Start Date: September 2016
Projected Completion Date:
December 2017
Completion Date: December 2017
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Carmansville Playground, Manhattan
Amsterdam Avenue between West 151st Street and West 152nd Street
Community Board: 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025