Bennerson Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Samuel N. Bennerson Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2013
Projected Completion Date: June 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: November 2016

Construction

Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: January 2018

Understand how we build parks.

Funding

Total Funding: $2,512,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Samuel N. Bennerson 2nd Playground, Manhattan
West 64th Street between Amsterdam Avenue and West End Avenue, Manhattan
Community Board: 07

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025