Jackie Robinson Recreation Center Exterior Facade & Roofing Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the exterior facades and roof of Jackie Robinson Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2014
Projected Completion Date:
May 2014
Completion Date:
June 2016
Procurement
Start Date: June 2016
Projected Completion Date:
February 2017
Completion
Date:
February 2018
Construction
Start Date: March 2018
Projected Completion Date:
March 2020
Completion Date: March 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Jackie Robinson Park, Manhattan
Bradhurst Avenue between West 145th Street and West 147th Street
Community Board: 09, 10
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025