Chelsea Recreation Center Locker Room Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the men's and women's locker rooms at the Chelsea Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2014
Projected Completion Date: October 2015
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: October 2017
Completion Date: June 2018

Construction

Start Date: September 2018
Projected Completion Date: March 2020
Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $2,767,000
Funding Sources:
  • City Council
  • Mayoral

Location

Chelsea Recreation Center, Manhattan
430 West 25th Street
Community Board: 04

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024