Chelsea Recreation Center Locker Room Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the men's and women's locker rooms at the Chelsea Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2014
Projected Completion Date:
October 2015
Completion Date:
February 2017
Procurement
Start Date: February 2017
Projected Completion Date:
October 2017
Completion
Date:
June 2018
Construction
Start Date: September 2018
Projected Completion Date:
March 2020
Completion Date: March 2020