Hinton Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the northern and southern portions of Hinton Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: December 2014
Completion Date: February 2015

Procurement

Start Date: February 2015
Projected Completion Date: November 2015
Completion Date: November 2015

Construction

Start Date: November 2015
Projected Completion Date: November 2016
Completion Date: July 2016

Understand how we build parks.

Funding

Total Funding: $1,203,000
Funding Source: City Council

Location

Hinton Park, Queens
Bounded by 113th and 114th Streets and 34th and 37th Avenues
Community Board: 03

 

Project Staff

Project Liaison: Meira Berkower