Bronx Park Brady Playground Adult Fitness Equipment Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct adult fitness equipment and miscellaneous site work and convert a tennis court to a basketball court in Bronx Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2014
Projected Completion Date:
December 2014
Completion Date:
January 2015
Procurement
Start Date: January 2015
Projected Completion Date:
October 2015
Completion
Date:
January 2016
Construction
Start Date: March 2016
Projected Completion Date:
March 2017
Completion Date: January 2017
Understand how we build parks.
Funding
Funding Source: City Council
Location
Bronx Park, Bronx
Bronx Park East between Brady Avenue and Unionport Road
Community Board: 06, 07, 11, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024