Manhattan Roofing Systems Reconstruction (MG-614M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct roofing systems in Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2013
Projected Completion Date: January 2014
Completion Date: March 2014

Procurement

Start Date: March 2014
Projected Completion Date: December 2014
Completion Date: July 2015

Construction

Start Date: September 2015
Projected Completion Date: September 2018
Completion Date: September 2017

Understand how we build parks.

Funding

Total Funding: $929,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024