Joe Michael's Mile Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the southern portion of Joe Michael's Mile.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2014
Projected Completion Date:
January 2016
Completion Date:
April 2016
Procurement
Start Date: April 2016
Projected Completion Date:
January 2017
Completion
Date:
June 2017
Construction
Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date: August 2018
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Federal
- Mayoral
Location
Cross Island Parkway, Queens
28th Avenue to Northern Boulevard
Community Board: 07, 11, 13